Wabagishik

Ontario, Canada

Ontario, Canada

Location

2019-2021

Year of realization

Vale

Owner

Installation

Type of services

The project

Installation and commissioning of 4 spillway gates including all the mechanical equipment related to the new Wabagishik Dam project.

Installation :

  • Embedded parts for the 4 sluices (sills and guides)
  • On-site assembling of the 4 gates of 12.25 tonnes (27 000 lb) each
  • 4 hoists support structure
  • Housing and commissioning of the hoists
  • Storage and lifting system for stop logs
M2i
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.