Wabagishik

Ontario, Canada

Ontario, Canada

Location

2019-2021

Year of realization

Vale

Owner

Installation

Type of services

The project

Installation and commissioning of 4 spillway gates including all the mechanical equipment related to the new Wabagishik Dam project.

Installation :

  • Embedded parts for the 4 sluices (sills and guides)
  • On-site assembling of the 4 gates of 12.25 tonnes (27 000 lb) each
  • 4 hoists support structure
  • Housing and commissioning of the hoists
  • Storage and lifting system for stop logs